How to buy industrial machinery from Germany for a plant in Egypt or the Gulf

Updated 9 min read By Farres Nagaa, Rekrutieren, Dortmund

On this page
  1. Should you buy new or used machinery from Germany?
  2. Where do you buy machinery in Germany?
  3. How do you write a specification German suppliers can quote on?
  4. Will a German machine run on your power supply?
  5. Which documents, approvals and manuals do you need?
  6. How do you test and pack the machine before it ships?
  7. What happens after arrival: installation, commissioning and warranty?
  8. How Rekrutieren handles this
  9. Frequently asked questions
  10. Sources

Short answer

Write a clear specification first, then buy new machines from German manufacturers or used ones from dealers and auctions. Confirm the machine suits your power supply: Germany runs at 50 Hz, Saudi Arabia at 60 Hz. Test it at the factory before shipping (FAT), pack it seaworthy, and agree installation, warranty start and spare parts in the contract.

This guide is for plant managers, engineers and purchasing teams in Egypt, Saudi Arabia, the UAE and the other Gulf states who plan to buy production machines, lines or equipment from Germany. After reading it, you will know where to buy, what to specify, what to check on power and documents, and how to get the machine tested, shipped and running.

Should you buy new or used machinery from Germany?

Buy new when you need a defined output, a full warranty and current documents. Consider used when budget or availability matter more and the machine is a proven standard type.

New machinery Used machinery
Configuration Built to your specification, including voltage and frequency As it is; changes cost extra
Availability After the maker's production time Often soon, plus dismantling, overhaul and transport
Warranty From the maker, as the contract says From a dealer if agreed; at auctions often none
Documents Complete and current May be incomplete; check before you buy
Main risk Price and lead time Hidden wear, missing documents, outdated controls

Before buying a used machine, check:

  • Year of build, operating hours, and maintenance and repair records.
  • The machine running under power, ideally with your own material.
  • Whether the maker still supplies parts and software support for the controls and drives.
  • Who dismantles, packs and loads the machine, and by when.
  • Whether used machinery under that HS code may enter your country, and with which certificate. Ask your customs broker before you bid or pay.

Where do you buy machinery in Germany?

New machines come from manufacturers and their sales partners, used ones from dealers and industrial auctions. Trade fairs let you compare makers in a few days.

  • Manufacturers. Many German machine builders export directly or through regional partners. The member list of VDMA, the German machinery and equipment association, helps you find makers by sector.
  • Dealers. Used machinery dealers buy, overhaul and resell machines. Some offer a test run and a limited warranty in writing.
  • Auctions. Industrial auctions sell equipment from closed or insolvent plants. Read the terms: machines are usually sold as seen, the buyer often must remove them by a fixed date, and fees and VAT may be added to the price.

The major German trade fairs for machinery, as of November 2026:

Fair Focus Place Cycle Next edition
HANNOVER MESSE Industrial technology and automation Hannover Every year 5 to 8 April 2027
EMO Machine tools and metalworking Milan in 2027, Hannover in 2029 Every two years EMO Milano, 4 to 8 October 2027
interpack Processing and packaging Düsseldorf Every three years 10 to 15 June 2029
K Plastics and rubber Düsseldorf Every three years 18 to 25 October 2028
drupa Printing Düsseldorf Every four years 9 to 17 May 2028

How do you write a specification German suppliers can quote on?

A user requirement specification (in German Lastenheft) states what the machine must achieve and under which conditions. For complex machines, the supplier replies with a Pflichtenheft describing how it will meet it.

Include at least:

  • Product and material. What the machine processes, with drawings or samples.
  • Output. Units per hour or per shift, tolerances and allowed scrap rate.
  • Site conditions. Highest and lowest ambient temperature, humidity, dust, floor space, ceiling height and crane capacity. Give your real summer peak: motors, drives and control cabinets have a maximum ambient temperature and may need extra cooling.
  • Utilities. Voltage, frequency and earthing system, compressed air, cooling water.
  • Controls. Preferred PLC (programmable logic controller) brand, operator screen language, remote access.
  • Scope. Installation, commissioning, training and spare parts.
  • Acceptance. Pass criteria for the factory test and the test at your site.
  • Delivery. The Incoterms rule and the exact delivery place.

Say you need a cup filler for a dairy in Jeddah. State cup sizes, fill volumes, output per hour, hall temperature in August, 400 V at 60 Hz, Arabic on the screen and the tests to pass before shipment.

Will a German machine run on your power supply?

Voltage is rarely the problem, frequency often is: Germany, Egypt and the UAE use 50 Hz, Saudi Arabia 60 Hz. A standard German machine needs changes for a Saudi plant.

Country Nominal three-phase voltage Frequency
Germany 400 V 50 Hz
Egypt 400 V 50 Hz
United Arab Emirates 400 V 50 Hz
Saudi Arabia 400 V 60 Hz

Qatar, Kuwait, Oman, Bahrain and Jordan also use 50 Hz. Saudi Arabia decided in 2010 to switch its household supply to 230 V but kept 60 Hz. These are nominal values, so measure the actual voltage at your plant and give it to the supplier.

What 60 Hz means for a machine built for 50 Hz:

  • Motors run faster. The speed of an induction motor rises in proportion to the frequency, so a 50 Hz motor turns about 20 percent faster on 60 Hz. Pumps, fans, conveyors and gearboxes then run at other speeds and loads than designed, and cycle times shift.
  • Drives help, but check the input. Motors on a frequency converter (variable frequency drive) take their speed from the drive, not the grid, but the drive must be rated for your supply.
  • Other parts. Transformers, power supplies, contactors and cabinet fans must also be rated for your frequency.

Ask the maker to confirm your voltage and frequency in writing and on the nameplate. German factory power is 50 Hz, so ask how it will test a 60 Hz machine before shipment.

Which documents, approvals and manuals do you need?

Ask for a complete document set in a language your team reads, and check which approvals your country requires. CE marking alone is not an import approval in Egypt or the Gulf.

CE marking is the maker's declaration that a machine meets EU rules for the EU market. Machines placed on the EU market before 20 January 2027 follow the Machinery Directive 2006/42/EC; from that date the Machinery Regulation (EU) 2023/1230 applies. A machine built in Germany only for export is not placed on the EU market, so CE marking is not automatic. If you want it, put CE marking and an EU Declaration of Conformity in the contract.

Destination approvals depend on the country and the HS code. In Saudi Arabia, products covered by SASO technical regulations need a Product Certificate of Conformity and a Shipment Certificate through the SABER platform, requested by the importer. See our guides for Saudi Arabia and Egypt.

Export controls apply to some machines. Certain machine tools and production equipment are on the EU dual-use list (Category 2, materials processing, in Annex I of Regulation (EU) 2021/821). BAFA, the German export control authority, decides whether a licence is needed. See our guide on export controls.

Ask for these documents:

  • EU Declaration of Conformity, if the machine is CE marked.
  • Operating and maintenance manuals, and a spare parts list with part numbers.
  • Electrical, hydraulic and pneumatic diagrams, and a PLC program backup with its terms of use.
  • Foundation and layout drawings with utility connections.
  • Test certificates for pressure equipment and lifting gear, where they apply.
  • The signed factory test report.

Agree in the contract which languages the manuals, operator screen and warning signs use, and put Arabic in the specification early if you need it.

How do you test and pack the machine before it ships?

Test the machine at the maker's factory in a Factory Acceptance Test (FAT) before you release it, then have it packed for sea transport. Faults are easier and cheaper to fix in Germany than at your site.

  1. Agree the FAT protocol in the contract: what is tested, with which material, for how long, and the pass criteria.
  2. Send your material or packaging samples to the maker in time.
  3. Attend in person, send an inspector, or follow by live video. See our guide on pre-shipment inspection.
  4. Check output, tolerances, safety functions (emergency stops, guards, interlocks), nameplate data and documents.
  5. Sign the FAT report with a list of open points. Release shipment only when those points are closed or agreed in writing.
  6. Link a payment milestone to the signed FAT report.

For packing, ask for:

  • Seaworthy crates on skids, corrosion protection on bare metal (such as VCI film) and desiccant bags against condensation.
  • Solid wood crates, pallets and dunnage treated and marked under ISPM 15, the international standard for wood packaging. Confirm your country's current rule with your forwarder.
  • Centre of gravity, lifting points and weights marked on each crate, and a packing list per crate.
Shipping option Use it for
Standard container (20-foot or 40-foot) Machines that fit through the doors, loaded by forklift
High cube container The same, but taller
Open top container Tall machines craned in from above, covered with a tarpaulin
Flat rack Wide or heavy machines; needs lashing and weather protection
Breakbulk (conventional cargo) Very large units shipped without a container

What happens after arrival: installation, commissioning and warranty?

Prepare the site, have the maker commission the machine or supervise it, run a Site Acceptance Test (SAT), and settle warranty start and spare parts in the contract.

  1. Before shipment, build the foundation to the maker's drawings, prepare power, air and water connections, and check access routes, doors and lifting equipment.
  2. Arrange visas for the maker's technicians.
  3. Install and commission with the maker's technicians, or under their supervision with a local contractor.
  4. Run the SAT with your material, using the FAT criteria under real conditions, and sign a handover protocol.
  5. Train operators and maintenance staff.

Warranty start. Agree in writing when the warranty starts: at delivery, at commissioning or at the signed SAT. Add a latest start date, so a delayed installation neither uses up the warranty nor leaves it open. Define what is excluded, such as wear parts, and who pays travel costs for warranty visits.

Spare parts and service. Get a recommended spare parts list with part numbers and prices, and ship critical spares with the machine. Ask in writing how long the maker will supply parts for this model, whether it has a service partner in your country, and how remote diagnosis works.

How Rekrutieren handles this

Rekrutieren is a German B2B sourcing and purchasing agency at Wittbräucker Straße 4, 44287 Dortmund (rekrutieren.com), and machinery and equipment is one of the sectors we work in for businesses in Egypt, Saudi Arabia, the UAE, Qatar, Kuwait, Oman, Bahrain and Jordan. We find German manufacturers and distributors that fit your specification, check their company records, certificates and references, and negotiate price, terms and lead times in German. Before the machine leaves Germany, we inspect it and send you photos and a written report, and we coordinate shipping and customs to Egypt or the Gulf. You have one contact from first enquiry to delivery, updates in Arabic or English, and a written quote with every cost before anything is ordered. Send us your specification or a short description of the machine you need.

Get a free quote

Frequently asked questions

Can a 50 Hz machine be converted to 60 Hz later?

Sometimes, but it can mean new motors, changed gear ratios or new drives. It is simpler to order the machine for your frequency from the start.

Who pays for the maker's technicians during installation?

It depends on the contract. If installation is not in the quote, get daily rates, travel and accommodation costs in writing before you order.

Should I visit a trade fair or the factory?

Both. A fair helps you compare makers quickly; the factory visit and the FAT are where you check your own machine.

What insurance do I need for shipping a machine?

Insure it from the maker's door to your site, including loading, transshipment and unloading, and check who buys the cover under your Incoterms rule.

Sources

  1. European Commission: Machinery
  2. World Standards: Three-phase electric power by country
  3. World Standards: Saudi Arabia plugs and voltage
  4. ACHR News: Line frequency and motors
  5. Intertek: Saudi SABER system overview
  6. IPPC: Guide to regulation of wood packaging material
  7. BAFA: Export control

General information, not legal advice. Last checked: . This guide explains the rules as of the date above. Rules change, so confirm the current rule with the authority named in the guide or with your customs broker before you ship.

Written by Farres Nagaa Rekrutieren, Dortmund

Related

Keep reading.

(09) Free quote

Tell us what you need.

Send the details and we come back with suppliers, prices and lead times. No obligation.

  • Free and without obligation
  • A personal reply, not a bot
  • Every cost in writing

Your contact Farres Nagaa Dortmund, Germany