Short answer
Write the inspection into your purchase order before production starts. For series goods, book a pre-shipment inspection when production is finished and use AQL sampling under ISO 2859-1. For machinery, hold a factory acceptance test (FAT) at the maker's works. Check quantity, specification, workmanship, marking, seaworthy packing and documents such as the EU declaration of conformity and EN 10204 3.1 certificates.
This guide is for buyers in Egypt, Saudi Arabia, the UAE and the other Gulf states who order machinery, components or series goods from German manufacturers and distributors. After reading it, you will know which inspection to book, what to check, which documents to ask for, who pays, and how to write it all into your purchase order.
What types of inspection can you order before goods leave Germany?
There are four common checkpoints: an inspection during production, a pre-shipment inspection, loading supervision and, for machinery, a factory acceptance test. You can combine them.
| Inspection | When it happens | Main purpose | Typical use |
|---|---|---|---|
| During production inspection | First finished pieces exist | Find problems while they are cheap to fix | New suppliers, custom parts |
| Pre-shipment inspection (PSI) | Production finished, most goods packed | Compare finished goods with the order before you pay the balance | Series goods, spare parts |
| Loading supervision | During loading | Confirm goods, count and securing, record the seal number | Full containers, high-value cargo |
| Factory acceptance test (FAT) | Machine assembled at the maker's works | Prove the machine meets the specification before packing | Machinery, production lines |
Say you order 2,000 stainless steel flanges for a plant in Jeddah: a pre-shipment inspection plus the right material certificates covers the main risks. For a filling line for a dairy in Sadat City, the FAT matters most. See also our guide on buying machinery from Germany.
How is a factory acceptance test (FAT) different from a site acceptance test (SAT)?
A FAT takes place at the manufacturer's works in Germany before shipment. A site acceptance test (SAT) takes place after installation at your plant. The FAT proves the machine works as specified. The SAT proves it works in your factory, with your power supply, your utilities, your materials and your staff.
| Factory acceptance test (FAT) | Site acceptance test (SAT) | |
|---|---|---|
| Place | Supplier's works in Germany | Your site in Egypt or the Gulf |
| Timing | Before dismantling and packing | After installation and commissioning |
| What it proves | Functions, output, safety devices and software meet the specification | The machine performs in real operating conditions |
A FAT should follow a written test protocol that both sides sign before the test date. Run the machine with your own product samples if you can, test every safety function and record output. If your contract links the final payment or the start of the warranty to the SAT, define the SAT criteria as precisely as the FAT. For automation systems in the process industry, the standard IEC 62381 (current edition 2024) describes the FAT, the SAT and the site integration test (SIT) and gives checklists. For other machines, the contract defines what each test includes.
What does a pre-shipment inspection check?
A pre-shipment inspection compares the finished, packed goods with the purchase order, the drawings and any approved samples. A good checklist covers five areas.
- Quantity: count the pieces and packages and compare them with the order, the packing list and the invoice.
- Specification: measure dimensions, confirm materials, model numbers and ratings, and check that voltage and frequency match what you ordered for your plant.
- Workmanship: look at welds, surfaces, paint, burrs, cleanliness and transport damage, and run a function check on a sample.
- Marking and labels: check nameplates, part numbers and shipping marks on every package (consignee, order number, package number, weights, handling symbols). Under the EU Machinery Directive, a machine must be marked with the maker's name and address, the designation, the CE marking, the series or type, the serial number and the year of construction. Your country may require further labels, see for example our Egypt guide.
- Packing for sea freight: goods going by sea need seaworthy packing, usually closed wooden crates, the item fixed inside, protection against moisture and corrosion, and lifting points and the centre of gravity marked on the crate. Many German machine builders refer to the packing guidelines of HPE (Bundesverband Holzpackmittel, Paletten, Exportverpackung) as their minimum standard. Crates and pallets of raw wood should meet ISPM 15, the international standard for wood packaging, and carry the IPPC treatment mark. Plywood is outside ISPM 15.
Which documents should you check before shipment?
Documents prove what an inspector cannot see, such as material composition. Name every document in the purchase order and check it before the goods leave.
| Document | What it shows | When to ask for it |
|---|---|---|
| EU declaration of conformity and CE marking | The maker declares the product meets the EU rules that apply to it | Products that need CE marking, such as machinery and electrical equipment |
| Declaration of incorporation | The unit is partly completed machinery, to be built into a larger machine | Machine modules without their own CE marking |
| EN 10204 inspection certificate 3.1 | Test results from specific inspection, validated by the maker's inspection representative, independent of production | Steel, pipes, flanges, castings |
| Test reports | Pressure, electrical or performance tests, the signed FAT protocol | As agreed |
| Manuals and drawings | Operation, maintenance, spare parts, wiring diagrams | Machinery |
Check that the declaration of conformity names the exact model and serial number, lists the EU legislation and standards applied, and is signed and dated. On a 3.1 certificate, the heat or batch number must match the marking on the parts. A type 2.2 test report only gives results from non-specific inspection, which need not come from the delivered batch. If you want a third party or your own representative to witness the tests, order a type 3.2 certificate.
CE marking is an EU market rule. For goods going to Egypt or the Gulf, the destination's rules decide which certificates you need. The EU Machinery Regulation (EU) 2023/1230 replaces the Machinery Directive 2006/42/EC from 20 January 2027 and allows instructions in digital form. If you need printed manuals in English or Arabic, say so in the order.
How does AQL sampling under ISO 2859-1 work?
For series goods, you rarely check every piece. ISO 2859-1 gives sampling plans: from the lot size and the inspection level, you get a sample size and an accept or reject number for the AQL (acceptance quality limit) you chose. The current edition is ISO 2859-1:2026, which replaced the 1999 edition and added skip-lot procedures.
- Define defect classes in the order, usually critical (unsafe or illegal), major (the product fails or cannot be sold) and minor (cosmetic).
- Choose an AQL for each class. For critical defects, consider accepting none at all.
- The inspector draws a random sample from the finished lot.
- The inspector counts defects in each class and compares them with the acceptance number.
- The lot passes or fails. Over a series of lots, the standard's switching rules move to tightened or reduced inspection.
ISO defines the AQL as the maximum average percentage of defective items considered acceptable. It is not a promise that a lot has no defects, so defective pieces found in the sample must still be replaced or repaired. AQL sampling does not suit a single machine: for one-off equipment, use a FAT and a full inspection.
What should a good inspection report contain?
A good report lets you decide to release or hold the shipment without being there. Ask for these points:
- Order number, supplier, place, date and the inspector's name
- The checklist used and the sampling plan: standard and edition, inspection level, AQLs, lot size and sample size
- Quantity found against quantity ordered
- Results per checkpoint, with measured values, not only "OK"
- Defects by class, with counts and photos
- Function or test results that the inspector witnessed
- Documents checked, and documents still missing
- Photos of packing, crates and shipping marks
- For loading supervision: container number, seal number, and photos of the empty container, the loaded cargo and the sealed door
- A clear verdict (pass, fail or pending) with the reason
Who pays for the inspection?
Incoterms 2020 settle only part of the inspection costs. The rest you agree in the purchase order.
- Under the Incoterms 2020 rules, the seller pays for the checking operations needed to deliver the goods, such as checking quality, measuring, weighing and counting.
- A pre-shipment inspection required by authorities is part of export or import clearance. The party that handles that clearance under the chosen rule pays for it. Under FCA, for example, the seller pays for an inspection required for export and the buyer for one required for import.
- An inspection you order for your own protection is outside Incoterms. Normally the party that orders it pays, which is usually the buyer.
Agree in the order that the supplier pays for a second inspection if the goods fail the first one. For a FAT, agree who provides the test set-up, power, materials and staff, and who pays for your travel. Our guide to Incoterms for orders from Germany explains each rule.
How do you write inspection into the purchase order?
Put the inspection terms in the order before production starts, because the supplier has to plan access, timing and the consequences of a failed inspection. Cover these points:
- Type and timing: which inspections, at what production stage, and how many working days' notice the supplier gives before the goods are ready.
- Who inspects: your staff, your agent or an inspection company you name, with access to the works and, where needed, to sub-suppliers.
- Criteria: drawings, specifications, approved samples, the ISO 2859-1 edition (so both sides use the same tables), inspection level and AQLs, and the FAT protocol as an annex.
- Documents: declaration of conformity, 3.1 certificates, test reports and manuals, with the language you need.
- Packing and marking: seaworthy crates, ISPM 15 wood, shipping marks and labels.
- Failure: the supplier repairs or replaces at its own cost, pays for re-inspection, and the delivery date is adjusted only if you agree.
- Payment: link the balance payment, or a document under a letter of credit, to a passed inspection, and state that passing an inspection does not end the supplier's warranty.
Before you place the order, it also helps to check the supplier itself.
How Rekrutieren handles this
Rekrutieren inspects goods before they leave Germany and sends you photos and a written report. When we negotiate the order with the supplier in German, we write the inspection terms into the purchase order, so the date, the checklist and the required documents are agreed before production starts. We check certificates and declarations against the goods and the order, and we coordinate shipping, so the inspection result and the loading fit together. You get updates in Arabic or English from one contact. To plan an inspection for your next order, send us your enquiry.
Get a free quoteFrequently asked questions
Can I attend the inspection or FAT myself?
Yes, if the purchase order gives you access to the works. Confirm the date in writing and plan for changes, because a FAT moves when production runs late.
What happens if the goods fail the pre-shipment inspection?
The supplier fixes or replaces the defective goods and a second inspection follows. Who pays for that second visit depends on your order, which is why the failure clause matters.
Is a "mill test certificate" the same as an EN 10204 3.1 certificate?
Not always. EN 10204 does not use the term "mill test certificate", so ask for an inspection certificate type 3.1 to EN 10204 by name and check that the document says 3.1.
Does a passed inspection replace the supplier's warranty?
No. An inspection only checks a sample at one moment. Hidden defects remain covered by the warranty in your contract, so state this in the purchase order.
Sources
- ISO 2859-1:2026, Sampling procedures for inspection by attributes, Part 1 (ISO)
- DIN EN 10204:2005-01, Metallic products, types of inspection documents (DIN Media)
- IEC 62381:2024, Factory acceptance test, site acceptance test and site integration test (IEC)
- CE marking (Your Europe, European Union)
- Directive 2006/42/EC on machinery (EUR-Lex)
- Regulation (EU) 2023/1230 on machinery (EU-OSHA)
- Incoterms 2020 rules for any mode of transport (ICC)
- ISPM 15, Regulation of wood packaging material in international trade (IPPC)
General information, not legal advice. Last checked: . This guide explains the rules as of the date above. Rules change, so confirm the current rule with the authority named in the guide or with your customs broker before you ship.